International Projects

ECT Portfolio: International

ASSEMBLY OF MARLEY INDUSTRIAL COOLING TOWERS AT RAYONG, THAILAND

Contract Sum: RM480,000.00
Year of Project Completion: 2005

This project involved the assembly and erection work for an industrial cooling tower (Tower dimensions (L x W x H) = 87.9m x 13m x 16.2m) for the SMPC 3 Plant at Mat Ta Phut Industrial Estate, Rayong, Thailand. The scope of work include:-

  • Preliminary work – unloading, unpacking and inspection of materials prior to commencement of erection work
  • Assembly work – preparation of materials, erection, assembly and joint inspections with the Client Representatives (Marley Asia Pacific) and Owner Representatives (Mitsui Engineering and Shipbuilding)
  • Testing – conducted joint Mechanical Run Tests and Inspections which included the balancing and alignment of dynamic parts, final inspection before handing over to the Client.

ASSEMBLY OF MARLEY HVAC COOLING TOWERS, SINGAPORE

Contract Sum: RM120,000.00
Year of Project Completion: 2005

Effective Cooling Technologies was engaged by Marley Asia Pacific Pte Ltd to assemble and erect the HVAC cooling towers for the following newly built Mass Rapid Transport (MRT) Stations in Singapore: –

  • Boulevard MRT Station (3 units of cooling towers)
  • Nicoll Highway MRT Station (3 units of cooling towers
  • Millenia MRT Station (3 units of cooling towers
  • Convention MRT Station (3 units of cooling towers
  • Museum MRT Station (3 units of cooling towers
  • Dhoby Ghaut MRT Station (2 units of cooling towers